What approach is described when goals or priorities change near completion?

Prepare for the Customs and Border Protection Interview. Study through flashcards and multiple-choice questions with detailed hints and explanations. Ace your exam with confidence!

Multiple Choice

What approach is described when goals or priorities change near completion?

Explanation:
When goals shift late in a project, the best approach is to adjust the plan to finish in line with the new priorities rather than starting over. This means re-baselining what must be done, updating tasks, scope, and timelines as needed, and guiding the remaining work to a completion that still delivers the updated value. Doing so preserves progress already made and avoids waste, while staying responsive to stakeholder needs. Restarting from scratch would discard work already completed and rework effort. Doing nothing fails to address the new priorities, and panicking or derailing the project undermines progress and risk management.

When goals shift late in a project, the best approach is to adjust the plan to finish in line with the new priorities rather than starting over. This means re-baselining what must be done, updating tasks, scope, and timelines as needed, and guiding the remaining work to a completion that still delivers the updated value. Doing so preserves progress already made and avoids waste, while staying responsive to stakeholder needs. Restarting from scratch would discard work already completed and rework effort. Doing nothing fails to address the new priorities, and panicking or derailing the project undermines progress and risk management.